fig. 16
: smoke discharge sensor
fig. 13
: metal plates
fig. 14
: boiler wall / primary air openings
fig. 15
: boiler door
checK the smoKe DischarGe system seal
IT Is necessary To check ThaT The PerImeTer seal beTWeen The fan body on The boIler and The fan moTor Is InTacT and
comPleTe.
clean the combustion chamber
•
open the uPPer and cenTre door.
•
Push upwards and remove the steel profiles.
after removing all steel profiles, clean the walls of the boiler and primary air opening from deposits of ashes and soot. any ash residues must
also be removed completely from inside.
use The cleanIng Tools and an ash vacuum cleaner!
checK the boiler Door GasKets fig. 15
make sure ThaT all PerImeTer gaskeTs on The boIler’s doors are InTacT and comPleTe, and sealed. a functional check must
also be carried out regarding the status of the closing mechanisms (handles and hinges).
clean the smoKe DischarGe sensor fig. 16
loosen the fastening screw and remove the sensor from the smoke pipe.
Then clean the soot and dirt particles with a cloth.
checK safety valves (supplied as an optional accessory)
check The seal and oPeraTIon of all sysTem safeTy valves; make sure There are no WaTer leaks.
If operation is compromised, the valve must be cleaned or replaced.
thermal DischarGe valve checK (supplied as an optional)
make sure The Thermal dIscharge valve Is sealed and oPeraTIng, meanIng There Is no WaTer leak.
for this purpose, manually activate the thermal discharge valve.
If operation is compromised, the valve must be cleaned or replaced.