© Norsat International Inc.
(“Norsat”) All Rights Reserved
2021-12-20 DOC-001527 Rev A
6
Getting Started
This section will outline the RSW installation and setup.
2.1 Warnings
If the RSW is configured for AC power, before powering on the unit, make sure that
the system is properly grounded. This is required for safety purposes.
Do not open the ODU controller box lid while the system is powered on.
Inspect all cables for damage prior to connecting them to the system.
2.2 ODU Setup
2.2.1
Ku/Ka-Band LNB Installation
LNB installation for Ku-band and Ka-band components are identical, except different sized
fasteners are provided.
The following components are included with the LNB mounting kit.
Item 1 (Socket Cap Screw)
Item 2 (Washer)
Item 3 (Loctite)
8x for 1:1 RSW
12x for 2:1 RSW
8x for 1:1 RSW
12x for 2:1 RSW
1x
The following tools are required. (Not included with the mounting kit)
Tool 1 (Hex Key)
M2.5 for Ka-Band
M3 for Ku-Band
Note the interfaces shown below.