INITIAL COMMISSIONING OF THE FILTER
After your filter system has been installed and all hoses and pipes have been connected, fill the pool with water. If you
are using a built-in skimmer, fill with water up to the skimmer half (mark: water surface between the two arrows on the
skimmer flange).
It should be noted that the skimmer should always be so far submerged under water so that the pump is never able to
suck in air! Commissioning can begin once the water has reached the correct height from the installation skimmer.
Open the sliders on the tubing!
Open the coarse filter cover a little so that air can escape until water starts to flow out. Then close the cover again
(during this process air escapes from the coarse filter and the pump). The coarse filter must be filled with water for the
pump to suction.
Important: The pump must always be below the level of the water surface! Also open the vent screw on
the upper part of the tank so that the air can escape from the tank. As soon as the water flows out, tightly
close it again (only by hand, not with the tool!). It must be avoided that the pump runs dry. Fill the pump with
water before initial operation and after longer periods of inactivity. For this purpose, the coarse filter sieve
pot is filled to the brim with water.
If the filter system is properly vented, the first step is to backwash (as described below).
The screen basket must be cleaned from time to time. To do this, switch off the filter system, close all sliders and set the
6-way valve to the "closed" position.
Open the lid of the coarse filter sieve pot by unscrewing it to the left and remove the sieve basket. Rinse it well under
the water pipe and reinsert it in reverse order. Also grease the sealing ring of the pump cover with Vaseline.
Attention:
Do not forget to reopen the gate valves!
OPERATING INSTRUCTION 6-WAY VALVE
Summary of Contents for Duplex
Page 1: ...Betriebs und Montageanleitung Operation and installation manual NORSUP Duplex ...
Page 11: ......
Page 12: ...2 ERSATZTEILE FÜR BAUGRUPPE SF 400 SF 500 UND SF 600 1 3 5 4 2 ...
Page 14: ...Ersatzteile QS 400 QS 500 QS 600 12 11 28 29 14 22 15 26 19 25 13 21 17 16 18 20 23 27 ...
Page 25: ...2 SPARE PARTS FOR SF 400 SF 500 AND SF 600 ASSEMBLIES 1 3 5 4 2 ...
Page 27: ...Spare parts QS 400 QS 500 QS 600 12 11 28 29 14 22 15 26 19 25 13 21 17 16 18 20 23 27 ...
Page 28: ...MegaGroup Trade Holding BV PO Box 430 5460 AK Veghel Netherlands www norsup eu ...