Power-up procedure
4
Overview
Power-up procedures are used to inspect that the power cabling is correct and
to verify voltage checks.
Complete the power-up procedure before any equipment is plugged into the
equipment shelves.
Perform the procedure whenever a shelf or a unit such as the Alarm Control
Unit (ACU), the DualMode Cell Site Monitor (DCSM), or the High Stability
Master Oscillator (HSMO) is either removed or replaced. If the voltage or
polarity of the DC power is incorrect, equipment damage may result.
DC power inspection
An orderly installation of DC power is required at the enclosure to ensure
ease of expansion as traffic increases.
Step
Action
Observation
1
Verify that the DC power cables from the
breaker panel on the power bay to the
equipment bays have been run in an orderly
fashion and are secured to the runway.
2
Verify that the lugs have been installed
correctly and, if terminated on aluminum
busbars, have been treated with anti-oxidant.
3
Verify that the minimum bending radius has
not been exceeded on the power cables (see
Table 4-1).
Summary of Contents for DualMode 800
Page 2: ......
Page 4: ......
Page 6: ...vi Publication history Nortel Networks Confidential 411 2051 500 Draft 00 01 November 1999...
Page 82: ...2 20 Periodic maintenance 411 2051 500 Draft 00 01 November 1999...
Page 90: ...3 8 Test equipment and precautions 411 2051 500 Draft 00 01 November 1999...
Page 100: ...5 6 Master Oscillator tests 411 2051 500 Draft 00 01 November 1999...
Page 106: ...6 6 Antenna and transmission line tests 411 2051 500 Draft 00 01 November 1999...
Page 116: ...8 4 Alarm Control Unit ACU tests 411 2051 500 Draft 00 01 November 1999...
Page 138: ...10 2 ICRM tests 411 2051 500 Draft 00 01 November 1999...
Page 200: ...12 10 Enclosure maintenance 411 2051 500 Draft 00 01 November 1999...
Page 208: ...A 8 Appendix A Frequency table 411 2051 500 Draft 00 01 November 1999...
Page 215: ......