11.9 Electric Heaters
An air handling unit would normally require no heater maintenance.
However a periodic check is advised to ensure that the fasteners and
electrical connections are operating correctly.
The electric heater unit is fitted with fail-safe thermal switches (self-
resetting) which will isolate the electric heater supply if a temperature
of 80°C is detected. This action is performed independently of any
controls fitted. Nuaire fitted controls will also stop heating if a fan or
heater failure is detected.
11.10 Bulkhead Lights
Ensure that lights are switched off and isolated before checking or
changing the lamp.
11.11 General
Inspect all internal and external surfaces to check for corrosion or
peeling of painted surfaces.
Thoroughly clean affected areas with a wire brush, apply a coat of zinc
rich primer or similar, and re-touch with suitable finishing paint. Ensure
tightness of all nuts, bolts, and fixings.
Check all components for general condition.
11.12 Specialist Equipment
Contact Nuaire for maintenance of specialised equipment that
would have been specified during design stage. A breakdown of the
component parts can be found on the design specification documents,
additional maintenance literature is available, please contact Nuaire.
This applies to any components not specifically mentioned in this
document.
11.13 Maintenance Schedule
11.13.1 Routine Maintenance
•
Clean all areas of unit and treat any areas of corrosion.
•
Check all access doors for leakage and if necessary locks should be
adjusted and any replacement gasket materials should be replaced
as required.
•
Any drain trays should be cleaned and repaired if necessary.
11.13.2 Every 3 Months
•
Check filters and change/clean if required, failure to do so may
impair the performance and energy efficiency of this unit.
•
Ensure condensate drains are cleaned clear and that water can
flow freely from unit.
•
Check fin coil banks and heat exchangers. If necessary clean with a
soft brush or vacuum. Check for signs of contamination.
11.13.3 Annually
•
Thoroughly inspect the unit and its components for corrosion,
acting immediately to treat/restore any damaged areas.
•
All electrical terminals within the unit should be tightened.
•
Check all earth connections.
•
Check control dampers blades.
•
Check operation of damper actuators and linkages and adjust as
necessary.
•
Coil faces should be inspected and any dust removed.
•
Check any thermal wheel belt, motor, bearings, seals and if
necessary clean with a soft brush or vacuum cleaner.
12.0 WARRANTY
The 5 year warranty starts from the day of delivery and includes parts
and labour for the first year. The remaining period covers replacement
parts only.
This warranty is void if the equipment is modified without
authorisation, is incorrectly applied, misused, disassembled, or not
installed, commissioned and maintained in accordance with the details
contained in this manual and general good practice.
The product warranty applies to the UK mainland and in accordance
with Clause 14 of our Conditions of Sale. Customers purchasing from
outside of the UK should contact Nuaire International Sales office for
further details.
Failure to maintain the unit as recommended will invalidate the
warranty.
13.0 END-OF-LIFE AND RECYCLING
Where possible Nuaire use components which can be largely recycled
when the product reaches its end-of-life:
•
Fans, motors, controls, actuators, cabling and other electrical
components can be segregated into WEEE recycling streams.
•
Sheet metal parts, aluminium extrusion, heating/cooling coils and
other metallic items can be segregated and fully recycled.
•
EPP, plastic ducting, nylon corner pieces, plastic heat exchangers,
packaging material and other plastic components can be
segregated into mixed plastic and widely recycled.
•
Cardboard packaging, wood, used filters and other paper
components can be largely recycled or fully processed in energy
from waste centres.
•
Remaining Items can be further segregated and processed in
accordance with the zero waste hierarchy. Please call After Sales
Support for further information on items not listed above.
Ensure that Nuaire product is made safe from any electrical / water
/ refrigerant supplies before dismantling commences. This work
should only be undertaken by a qualified person in accordance with
local authority regulations and guidelines, taking into account all
site based risks.
14.0 AFTER SALES AND REPLACEMENT PARTS
For technical assistance or further product information, including spare
parts and replacement components, please contact the After Sales
Department.
If ordering spares please quote the serial number of the unit together
with the part number, if the part number is not known please give a full
description of the part required. The serial number will be found on the
identification plate attached to the unit casing.
Telephone 02920 858 400
aftersales@nuaire.co.uk
Technical or commercial considerations may, from time to time,
make it necessary to alter the design, performance and dimensions
of equipment and the right is reserved to make such changes without
prior notice.