Heating Cable Repair
58
|
nVent.com
Note
: If the Megohmmeter reading declines,
remove wet rag and visually inspect end cap for
pinholes. If pinholes exist, dry out cable according
to procedure in Appendix D, being careful not to trap
any moisture. Any remaining moisture will escape
through the pinhole. Once the moisture is removed,
touch up the braze as necessary and retest. If still
low or if no pinholes are visible, replace end cap.
Caution: Endcap will be hot. Do not touch endcap
or cable with bare hands.
Check resistance of heating cable using an ohmmeter
and compare with the measured value recorded in
Section 3.1. The resistance should not be any more than
3% lower than the value measured previously. If open
circuit, cut off end cap and repeat procedure.
The completed end cap is shown below (Figure 76).
Figure 76: Completed end cap
Install corrugate union and reinstall 12 in (30 cm) piece
of corrugate previously removed (Figure 77).
Corrugate union
Corrugate
Figure 77: Install union and corrugate
Clean and polish both ends of the corrugate and the corrugate
union with the nylon mesh sanding pad. The surfaces must be
clean for the silver braze to adhere to them.