After connecting to the hose assembly, an ope-
rational test shall be performed. It is essential to
examine that the nozzle, hose connector and
swivel are tight under pressure and do not leak
– e.g. by external application of foaming agents.
NOTE : Pressurise system gradually while
checking for leaks.
Always put back the nozzle into the nozzle
holder.
ATTENTION: Do not drop.
Do not leave on the floor
TROUBLESHOOTING
•
If the lever cannot be pulled back
Check the correct seating of the nozzle to the vehicle coupling. Make sure you push the
nozzle straight and aligned towards the receptacle. A safety feature prevents operation of the
nozzle if the connection is misaligned. If you have any doubts or questions, please contact the
station personnel.
Never force operation of the nozzle
. If the connection process does not work smoothly,
disconnect and re-connect nozzle as indicated under 'Operation Instructions'.
•
Leakage ( escaping gas )
A small gas release upon uncoupling is normal.
If uncontrolled and / or permanent gas
release to the atmosphere occurs, immediately stop fuelling
. If the leakage continues, push
emergency button of dispenser, leave area and inform station personnel.
If area is safe, check tight connection between vehicle connection and the N-CNG nozzle.
Check seals of vehicle connection and the N-CNG. If the problem persists, notify the station
personnel or the service contractor.
• If the latching does not work
:
Disconnect and re-connect nozzle as indicated under 'Operation Instructions'.
If it continues to not work properly or you have any doubts or questions, please contact the
station personnel.
• If the nozzle cannot be disconnected after refuelling
:
Connect nozzle once again as indicated under chapter 'Operation Instructions'. Then try to
disconnect and take off the N-CNG.
Never force operation of the nozzle. If the disconnection process does not work smoothly,
inform station personnel.
If self-service is not possible, please contact a service company specialised and certified in
CNG Service Station installations.