Installation Procedure 

The aim of all pit insert installations is to install the largest unit into each pit, without influencing the hydraulic 
performance of the pit or drainage system.  

Strut Install 

1.

 

Measure the internal dimensions of the pit while marking the center of the pit length, at 150mm 
down from entry of pit (the height where the struts are to be secured). 

 

2.

 

Mark the position of the holes for the L-brackets, based on the center mark 

 

3.

 

Using an 8mm masonry drill bit drill holes for the insertion of the Dyna Bolts  
(4 holes total, 2 per strut) 

 

4.

 

Attached L-brackets with dyna bolts to the pit wall (4 locations) 

 

 

 

 

 