00_200_202_03_01_002_AIR85-EN | www.ochsner.com 17
Machine-specific engineering and preparation
8.1.3 Installation in coastal areas
Please note the following with regard to installation in
coastal areas:
►
The standard version of the outdoor unit must be in-
stalled at least 1 km from the sea.
►
Outdoor units with special coating, suitable for coast-
al locations, must be installed a minimum of 200 m
from the sea.
►
The installation location selected should always be on
the leeward side of the building (the side facing away
from the sea).
8.1.4 Foundation for the outdoor unit
Spot foundation
1 Gravel bed
2 Drainage pipe (frostproof)
3 Spot foundation (with underground sewer pipe)
A
B
C
D
AIR 85
1870
250
935
2045
Use underground sewer pipes when installing spot foun-
dations.
When installing spot foundations, we recommend the fol-
lowing approach:
»
Dig out the foundation trench.
»
Lay the underground sewer pipes in position.
»
Ensure correct horizontal and vertical positioning of
the underground sewer pipes.
»
Place a drainage pipe along the base of the trench.
1 Underground sewer pipe
2 Drainage pipe (frostproof)
3 Gravel bed
»
Fill the foundation trench with coarse gravel.
»
Fill the underground sewer pipes with concrete.
Summary of Contents for 288800V
Page 2: ......
Page 7: ...PIA 982027 AIR 85 sh EN www ochsner com 7 ...
Page 9: ...00_400_200_202_01_split_Funktionsweise EN www ochsner com 9 How split systems work ...
Page 45: ...PIA 982027 AIR 85 td EN www ochsner com 45 System principle schematic ...
Page 53: ...PIA 982027 AIR 85 EN01 www ochsner com 53 ...
Page 54: ...Notes ...
Page 55: ...Notes ...