PIA-982027-AIR 85-in-EN | www.ochsner.com 39
Completion and commissioning
►
Version 2:
Where connection lines have been laid and the tech-
nical installation of the refrigerant circuit carried out
by OCHSNER customer service.
WARNING: Burns
Work on the refrigerant circuit may be carried out
only by OCHSNER Customer Service or by cus-
tomer service partners authorised by OCHSNER.
12.3 Commissioning the system
All the necessary requirements must be met before com-
missioning. (See pages 37, Requirements)
Commissioning is carried out by OCHSNER customer
service or by a customer service partner authorised by
OCHSNER.
Information
If the system is operated without professional
commissioning in accordance with the OCHSNER
guidelines, all warranty claims will be invalid.
Information
Special work such as system venting, connecting
electrical cables, additional training, etc., which is
not included in OCHSNER’s scope of delivery, will
be invoiced separately.
12.3.1 Activities carried out by OCHSNER
►
Checking that the system has been installed ac-
cording to the machine-specific engineering and
installation information. In commissioning the system,
OCHSNER offers no warranty regarding the ability to
meet the heat demand of the building to be heated.
►
Functional testing of the heating circuit (system pres-
sure, function of diaphragm expansion vessel, flow
rate settings). Responsibility for the system remains
with the system installer.
►
Checking the flow rates.
►
Checking that all shut-off valves are open.
►
Checking the electrical connections to the system
components including all required safety devices.
►
Switching on the main power circuit (3-phase supply
to heat pump).
►
Switching on the power supply to the control circuit.
►
System configuration.
►
Checking the sensor configuration.
►
Conducting a relay test on the outputs.
►
Making customer-specific settings on the heat pump
system.
►
Producing a commissioning report and completing
the entries in the service book.
►
Handing the system over to the system user or end
customer.
►
Explanation of the basic functions of the heat pump
system (controller operation, etc.).
►
Preparation of a Declaration of Conformity according
to the Pressure Equipment Directive 2014/68/EU for
the entire system (in countries where the Pressure
Equipment Directive 2014/68/EU is valid).
Information
If the system is not commissioned by OCHSNER
customer service, but by a customer service part-
ner authorised by OCHSNER, a declaration of
conformity in line with Pressure Equipment Direc-
tive 2014/68/EU must be issued by this partner.
Information
OCHSNER Customer Service will provide an ex-
planation of the basic functions of the heat pump
system (controller operation, etc.). If the system
user is not present for commissioning, the system
installer will assume responsibility for this explana-
tion. Instruction on the functionality of the overall
system is the responsibility of the system installer.
Summary of Contents for 288800V
Page 2: ......
Page 7: ...PIA 982027 AIR 85 sh EN www ochsner com 7 ...
Page 9: ...00_400_200_202_01_split_Funktionsweise EN www ochsner com 9 How split systems work ...
Page 45: ...PIA 982027 AIR 85 td EN www ochsner com 45 System principle schematic ...
Page 53: ...PIA 982027 AIR 85 EN01 www ochsner com 53 ...
Page 54: ...Notes ...
Page 55: ...Notes ...