The machine may be delivered to the customer either fully assembled or partly separated due to transporting issues, and complete
assembly must be performed by skilled and instructed personnel, who possess the required expertise, technical knowledge,
documentation and equipment.
For proper machine assembly, comply with the specifi c technical documentation, consisting of:
•
General machine drawings
•
Connection diagram
•
This manual
•
Manuals for the main trade components installed on the machine.
NOTE
The spreader beam, 3000 mm / 118.11 in long chains or ropes with load capacity compliant with the weight to be lifted (see
chapter 2 for the individual model) are not supplied with the machine.
It is the customer's responsibility to procure them and make them available.
The Manufacturer indicates the lifting points fi tted on the machine, which must always be checked before use by the personnel
in charge.
TILTING HAZARD
•
Should the machine need to be moved on uneven, muddy or slippery terrain or near potholes or slopes, exercise extreme
caution and use low speeds. In any case never exceed 10 km/h when towing the raingun, even on roads.
•
Do not move the machine if the terrain conditions are hazardous and if no measures have been taken to prevent a possible
tilting hazard.
•
Do not manoeuvre crosswise on slopes, as this might lead to the machine overturning.
•
In any event, never travel on grades exceeding 8.5°.
DANGER OF HITTING PERSONS OR PROPERTY
•
Prior to performing any machine movement, ensure there are no persons or property within the operating area, since the
position of the controls on one side does not afford fully unrestrained visibility.
•
Do not move the machine if there are any people near its manoeuvre area.
HAZARD IN PARKING THE MACHINE
•
Always park the machine on level ground.
•
Lower the front stabiliser leg, the rear anchoring legs and the raingun trolley to the ground.
•
If the machine is road-approved and it needs to be parked in a public area for any reason, the parking brake needs to be
engaged if the machine is equipped with it or use wheel stop wedges.
NOTE: TRAVEL ON PUBLIC ROADWAYS
The machines in question may travel on public roadways only if approved complying with the laws in force in the country of
destination, and the maximum speed they may be towed at is generally 40 km/h for Italy and 25 km/h for France. (the recommended
speed on public roads is 20÷25 km/h).
Prior to travelling on public roadways, the correct operation of visual indication systems and the effi ciency of the braking system,
where provided, must always be checked.
The features of the systems for type-approved machines vary depending on the country of destination.
5.5
LUBRICATION OF MACHINE PARTS
After completing the power supply connection and prior to starting up, check whether any machine parts need to be lubricated.
For the above operations please refer to this manual under chapter 7 “MAINTENANCE” in the paragraph covering the “Lubrication Plan”.
Summary of Contents for MR
Page 99: ......