1. Connection of the weighing cell measuring signal
1
red (signal –)
2
white ()
3
GND
4
grey and black (GND)
5
blue and green (0–10
Volt)
2. Connection of the measuring signal to the Boiler controller
The polarity of the measuring signal connection must correspond to the following diagram:
The terminal of the circuit
board furthest from the
marking X3 is always terminal
5 on the plug of the Boiler
controller (0–10 Volt).
The terminal closest to the
marking X3 is always terminal
6 on the plug of the Boiler
controller (GND).
Incorrect pin assignment:
The offset value is always dis-
played rather than the cur-
rent weight.
3. Connection of the power supply
ÖkoFEN recommends that
the power supply is always
connected to the weighing
system via the Boiler control-
ler. This ensures that the
whole installation is switched
off when the pellet system is
switched off.
5 Connection of the Weighing System
11
Installation manual
Summary of Contents for S158 EN 2.1
Page 1: ...Installation manual Weighing System Storage Tank ENGLISH S158 EN ...
Page 13: ......
Page 14: ......
Page 15: ......
Page 16: ......