6. Connect PC to Gateway
a. USB to Serial Adapter (SX1000-CC9)
b. Gateway Configuration Cable (SX1000-CC1)
7. Identify COM Port for use in BreeZ® (Device Manager)
8. Select a Gateway in BreeZ® Project Tree
9. Update Gateway with BreeZ® Project File
10. Confirm Gateway “Configuration Download OK” in
Build Tab Window in BreeZ®
11. Save Project File onto Gateway (For Backup)
4. Configuration Sequence - continued
2. Required Items
- DH1 - Base Unit Wireless Gateway
- External Power Source for Base Unit (9-30 VDC)
- Antenna for Gateway (Bulkhead, Omni, or Yagi)
- Antenna Cable (N to MMCX Connector)
- N to N Antenna Cable and Lighting Arrestor (Optional)
- External Enclosure for Base Unit (NEMA)
- DIN Rail (35 mm)
- USB to Serial Adapter (SX1000-CC9)
- Gateway Configuration Cable (SX1000-CC1)
- BreeZ® Configuration Software v5.0 or Higher
- PC
- S
crewdriver Set + Technician’s Screwdriver
- Any Additional Tools for Installation
- RS485 I/O Expansion System (Optional)
CAUTION
: Field wiring connections shall be made in accordance
with Article 504 of the National Electrical Code, ANSI/NFPA70.
CAUTION
: The Base Unit must be installed within an enclosure
that requires a tool to access. This is to prevent inadvertent
disconnection of any of the power wiring, signal wiring or
communication cables.
ATTENTION
: Le
Base Unit doit être installé dans une enceinte qui nécessite
un outil d'accès. Ce est pour éviter toute déconnexion accidentelle de l'un
des câbles câblage de puissance, câblage ou de communication signaux.
WARNING
: Ensure installation of the Gateway meets applicable
state and national electrical code requirements. The installation
of the Base Unitshould only be performed by a qualified installer or a
factory representative.
AVERTISSEMENT
: Veiller à l'installation de la passerelle répond Etat et
des exigences nationales de code de l'électricité. L'installation de la
Base Unit ne doit être effectuée par un installateur qualifié ou un
représentant de l'usine.
WARNING
: To prevent ignition of flammable or combustible
atmospheres, disconnect power before servicing.
AVERTISSEMENT
: Pour éviter l'inflammation d'atmosphères inflammables
ou combustibles, débrancher l'alimentation avant l'entretien.
WARNING
: EXPLOSION HAZARD – Substitution of components
impair suitability for Zone 2.
AVERTISSEMENT
: RISQUE D'EXPLOSION - Le remplacement de composants
nuire à la conformité pour la Zone 2.
WARNING
: EXPLOSION HAZARD – Do not separate/disconnect
connectors when energized.
AVERTISSEMENT
: RISQUE D'EXPLOSION - Ne pas séparer / débrancher les
connecteurs lorsque excité.
WARNING
: EXPLOSION HAZARD – Do not service when an
explosive atmosphere is present.
AVERTISSEMENT
: RISQUE D'EXPLOSION - Ne pas service lorsque une
atmosphère explosive est présente.
WARNING
: EXPLOSION HAZARD – Do not use reset switch in
hazardous area.
AVERTISSEMENT
: RISQUE D'EXPLOSION - Ne pas utiliser le commutateur
de réinitialisation en zone dangereuse.
1. Before You Begin
1. Download and install latest BreeZ® Software v5.0 or
higher to a PC (see section 3)
2. Check for latest Base Unit Firmware on Download Center
3. Create a BreeZ® Project File
*4. If upgrading Firmware, follow these instructions:
a. Physically Connect Gateway to PC
b. Supply power
c. Open Connect screen and click “Flash”
d. Locate new Firmware file and click “Open”
e. DO NOT DISCONNECT OR TURN POWER OFF while
upgrading Firmware (It may take a few minutes for
upgrading process to finish)
f. Wait until LED turns off
5. Power up Gateway (9-30Vdc) and wait until boot-up
sequence is complete
(LED will turn off once boot-up is complete)
3.
Configuration Sequence
80-3103-001_J
This guide provides basic information to assist you in quickly
getting started. Go to www.OleumTech.com to download the
full User Guide for detailed installation and other information.
5. Installation Sequence
1. Install Gateway inside a NEMA enclosure
a.
Remove Cover Using Two Top Screws.
b.
Adjust and Tighten DIN Rail Clamp
c.
Reattach Cover
2. Follow best grounding practices
3. Setup and connect an Antenna with Lightening Arrestor
to Gateway
4. Connect Gateway to third-party Serial device(s)
5. Power up Gateway
6. Power up/reboot any impacted sensors/devices if necessary
7. Verify RF and data communications
a. Use Modbus Register Polling and Write features in BreeZ®
b. Verify communication from third-party device(s) or
SCADA system
QUICK START GUIDE