43.
Attach end of a 68 1/4” long Soffit Board flush to ends of outside
rafters with 2 - 1 1/4” screws per rafter end.
Drill pilot hole in Soffit
ends to prevent splitting.
Complete both outside rafter / Soffit
connections first. Measure and position interior Rafters as illustrated
above. When positioned correctly, attach Soffits to remaining rafters
with 2 -1 1/4” screws /rafter. Flip completed rafter section over.
Complete Short Rafter Side as per
Steps 41 - 43
with the following
exception:
When attaching Ridge Board to Rafter ends, make
sure Metal Ridge Board Connector is positioned so offset to first
Rafter Section. See Step 48 for illustration.
42.
Attach completed Ridge Board to ends of both outside
rafters with 2 - 2” screws per end. Measure and position interior
Rafters as illustrated below. When positioned correctly, attach
Ridge Board to remaining rafters with 2 -2” screws /rafter end.
41.
Locate 9
Rafters
, 2
Soffits
and completed
Ridge Board. Lay out on level ground as shown to
the right. Double up Rafters as illustrated. Screw
doubled up Rafters together with 3 - 2 1/2” screws
per piece.
Note:
completed rafter section will be
flipped over in
Step 43.
Ridge Boards
Soffits
Rafter
Sof
fit
2 1/2” Screws
into Doubled
up Rafters
45.5”
68.25”
20.5”
20.5”
45.5”
20.5”
45.5”
20.5”
Metal Ridge Connectors
offset from Long and
Short Roof Sides
Short Rafter Side
Long Rafter Side
Important:
Pilot
Hole Ridge Board
and Soffit to
prevent splitting!
5 1/8” Ridge Board
4 5/8” Ridge Board
Soffit
Sof
fit
Ridge Board
Expert Advice:
Use Polygal
panel to confirm
correct width.
See
Step 66
.
Toll Free 1-888-658-1658 www.outdoorlivingtoday.com sales@outdoorlivingtoday.com