7.
Attach
Floor Runners
to completed floor
frame. There are 2 floor runners per
136 1/2” side and 5 completed runners in
total. Use 6 - 2 1/2” screws per Runner.
96”
5.
Complete all large and small frame attachments.
Screw each completed section together with 8 - 2 1/2”
screws.
6.
When completed, your floor footprint
should be 96” wide x 136 1/2” deep.
136 1/2”
8.
Make sure Runners are flush with
outside of framing, not overhanging.
3.
Lay out completed
Floor Joist Frames
as
illustrated. There are 3 larger and 3 smaller
Frame Sections. The Footprint for the floor when
attached together will be 96” wide x 136 1/2”
deep.
4.
Attach each large and small floor joist
frame together with 6 - 2 1/2” screws per
section.
Front of Shed