400433D-EN
3 - 1
Chapter 3
Operation
This chapter provides information and instructions supporting operation of the OMAX JetMachining Center. It
explains how the pump and abrasivejet system work and provides instructions on starting and stopping the
system and doing an emergency shut-down. It also discusses the JetMachining software, explains important
tasks to be performed in configuring the machine prior to cutting, lists tips for effective use of your equipment,
and outlines the steps involved in the cutting process from equipment power-up to power-down.
Note:
This manual does not provide detailed information on the operation of the OMAX Make and Layout
software. For instructions on using this software, refer to the OMAX Interactive Reference (the software
help screens), and software training videos available on the OMAX web site at http://www.omax.com/
support/customers/videos.asp.
Operating the High-Pressure Pump
WARNING!
When operating this equipment, always observe the safety precautions listed in Chapter 1 of
this document. Failure to do so can result in bodily injury or death.
When attached to an OMAX JetMachining Center, control is shared between the JetMachining Center
Controller and the pump keypad. The JetMachining Center turns the high-pressure pump ON to begin a cut
and turns it OFF between cuttings.
Before starting the pump unit:
1.
Check the pump’s maintenance log and other records for any ongoing service activities. Verify that no
“Out of Service” tags are posted on the pump’s main electrical disconnect or on its On/Off switch. If
service is scheduled and necessary, have it completed before resuming pump operation.
WARNING!
Before powering the pump for operation, verify that any equipment service is not in
progress.
2.
Visually inspect the pump components for damaged parts, leaks, and other conditions that could
prevent safe and proper operation. Ensure that the area around the pump is clear of tools and other
objects that could obstruct immediate access to controls functions, hindering safety.
3.
Verify that the oil level in the pump crankcase is sufficient for operation.
4.
Ensure that all pump side panels and enclosures are in place and properly secured.
5.
Familiarize yourself with the location and function of the controls identified previously in Figures 2-4
and 2-5.
Starting the Pump
WARNING!
Prior to starting the pump, verify that everyone is clear of the high-pressure cutting nozzle.
1.
Open the building’s inlet valve that provides water to the pump.
2.
Place the main electrical disconnect in the
ON
position.
3.
Turn the pump On/Off switch to the
ON
position (“I”).
4.
Turn the charge pump On/Off switch to the
On
position.
Summary of Contents for JetMachining Center 2626
Page 8: ...OMAX JetMachining Center Operator s Guide viii 400433D EN ...
Page 12: ...OMAX JetMachining Center Operator s Guide xii 400433D EN ...
Page 22: ...OMAX JetMachining Center Operator s Guide Safety First 1 10 400433D EN ...
Page 140: ...OMAX JetMachining Center Operator s Guide OMAX Glossary 6 16 400433D EN ...
Page 144: ...OMAX JetMachining Center Operator s Guide Index 4 400433D EN ...