Pagina 37 di 45
cod.ITRIP250092D
PRELIMINARY
TRIPARK 25
37
9.4.
Installing chemical anchors
After having correctly positioned the lift and after having checked that the
support bases are level, lock the lift to the floor of the shaft performing the
following operations in the order indicated:
1.
Drill holes in the floor of the shaft using the holes in the base of the lift
as point of reference.
2.
Fix the bars to the floor using chemical screw anchors, follow the
instructions provided by the screw anchor manufacturer for their
installation.
The installation sequence is as follows:
1. Drill a hole
2. Blow out all dust and fragments with compressed air
3. Insert
the
vial
4. Insert the anchoring substance
5. Wait until gelling has set in (t
rel
)
6. Wait for the compound to harden (t
cure
)
7. Tighten to set torque (T
inst
)
Lift levelling operations
may only be performed
after the machine’s wiring
and hydraulic connections
have been made.
ANCHOR DIMENSIONS
M16
PLASTIC LAMINATE VIAL
M16X125
THREADED BAR
M16X190
DIAMETER OF DRILL BIT
d
0
mm 18
HOLE DEPTH
h
1
(=h
nom
)
mm
125
MIN. THICKNESS OF BASE
MATERIAL
h(min) mm
170
MAX. THICKNESS TO BE
SECURED
t
fix
(max) mm
38
DIAMETER OF HOLE IN
PLATE
d
f
mm
cons. 18
max. 19
TORQUE
T
inst
Nm
100
PINS NUMBER
n°
6
°C t
rel
t
cure
-5°… 0°
60’ 5 h
0°… 10°
30’ 60’
10°… 20° 20’ 30’
20°… 40° 8’
20’