PRELIMINARY
TRIPARK 25
43
10. Check before using
The first time the lift started up it is essential to:
-
Clean and start up the system
-
Check that the limit switches are functioning properly.
-
Check the position of the limit switches to stop at the desired floors
-
Check floor leveling of the platforms and stopping precision
-
Check floor levelling and stopping precision
-
Check that the
floor push-buttons
are functioning properly
-
Check installation of warning signs - see chapter on Safety in the
User's Manual
-
Check that documentation is on hand - see chapter on Safety in the
User's Manual
After having performed all adjustments and controls, run a lift test running
it all the way up and down; this operation serves to check that the entire
machine is functioning properly and that there are no hydraulic system
leaks.
10.1.
Final testing
Static and dynamic overload tests are performed at the manufacturer's
premises.
The user can run checks with the rated load (a
10% variation due
maximum valve calibration is admissible) and with the loads distributed
as indicated in the paragraph on
Load conditions
in the User's Manual.
10.2.
Handing over the platform
The platform is handed over after having completed all the checks
indicated in the start-up report