41
SECTION 12
Checkout and Test procedure
12-1 Checkout Procedure
Once the F3S-TGR-CL system has been configured, mounted, aligned and
properly connected to the machine control system, the initial Checkout Proce-
dure detailed in Appendix A must be performed by qualified personnel. A copy
of the checkout results should be kept with the machine records.
12-2 Test Procedure
!WARNING
The tests outlined in the Test Procedure in Appendix B must be performed at
installation, according to the employer's regular inspection program and after
any maintenance, tooling change set up, adjustment or modification to the
F3S-TGR-CL system or the guarded machine. Where a guarded machine is
used by multiple operators or shifts, it is suggested that the test procedure is
performed at each shift or operator change. Testing ensures that the light cur-
tain and the machine control system work properly to stop the machine. Fail-
ure to test properly could result in serious injury to personnel.
The test procedure must be performed by qualified personnel.
12-3 Using the test object
When using the test object, guide it through the detection zone as shown:
Start
End
F06E-EN-03A+F3S-TGR-CL_K+OperManual.book Seite 41 Dienstag, 4. Oktober 2011 1:32 13