3-2-4
Commissioning Procedure
Use the following procedure to commission the Power Supply Box.
1
Prepare the facility AC supply and its disconnect switch.
2
Make sure that the facility power is in the OFF state.
3
Make sure that the main disconnect switch located on the electrical access panel is in the OFF
(horizontal) position.
4
Wire the facility power to the electrical access panel as detailed in
on page 3-6. You must make sure to adjust the jumpers as required for the voltage range.
5
Once the wiring is complete and the facility power cable is connected to the electrical access
panel properly, you can enable the AC facility power.
6
Confirm that the circuit breakers inside the electrical access panel are in ON positions (top / up
position).
3 Installation
3-7
HD-1500 Platform User's Manual (I645)
3-2 Charging Station Installation
3
3-2-4
Commissioning Procedure
Summary of Contents for HD-1500 Platform
Page 1: ...HD 1500 Platform User s Manual I645 E 03 ...
Page 6: ...Manual Information 4 HD 1500 Platform User s Manual I645 ...
Page 38: ...Revision History 36 HD 1500 Platform User s Manual I645 ...
Page 206: ...5 Troubleshooting 5 14 HD 1500 Platform User s Manual I645 ...
Page 236: ...6 Maintenance 6 30 HD 1500 Platform User s Manual I645 ...
Page 250: ...Appendices A 14 HD 1500 Platform User s Manual I645 ...
Page 251: ...I Index I 1 HD 1500 Platform User s Manual I645 I ...
Page 254: ...Index I 4 HD 1500 Platform User s Manual I645 ...
Page 255: ......