5-18
CHAPTER 5 Periodic Inspection
6) Remove the Y-axis arm installation bolts (M3×20L, 8 pieces). (See Fig. 5-7.)
Fig. 5-7
7) Remove the Y-axis arm and place it where it will not obstruct the work.
8) Remove the wave generator from the motor shaft. The wave generator is
secured with an M3 set screws (2 pieces). (See Fig. 5-10.)
9) Remove the flange installation bolts (M5×20, 6 pcs) and then detach
the flange from the X-axis arm. Next, remove the bolts (M3×20, 6 pcs)
securing the Y-axis harmonic drive. (See Fig. 5-8.)
Fig. 5-8
10) Remove the Y-axis harmonic drive from the flange.
M3
×
20
Do not remove these bolts.
Do not remove these bolts.
M5
×
20
M3
×
20
Flange
CAUTION
AN O-RING IS FITTED TO THE UPPER SURFACE OF THE HARMONIC
DRIVE, SO BE CAREFUL NOT TO LET IT DROP INTO THE PERIPHERAL
UNIT.
Summary of Contents for SCARA R6Y-XC Series
Page 2: ......
Page 10: ......
Page 12: ......
Page 29: ...CHAPTER 2 Functions 1 Robot Manipulator 2 1 2 Robot Controller 2 5...
Page 30: ......
Page 36: ......
Page 38: ......
Page 51: ...3 13 CHAPTER 3 Installation Fig 3 7 Ground terminal M4 Ground terminal Ground symbol...
Page 104: ......
Page 128: ......
Page 190: ......
Page 192: ......