Installation
31
-
Figure 12:
Terminal block
Designation
1. Ground
2. Shutter Status LED
3. Digital Input for Low-E measurement
4. Analog Input for opening/closing the shutters
5. 24 V Power supply
6. 24 V Power supply
7. 24 V Power supply
8. Ground
9. Ground
10. Ground
The wiring of the furnace signal on the control cabinet is done under connection 4 and connection 1 (ground).
The input voltage range is 0 / max. 24 V. An open input is interpreted as a high signal. The signal
must be switched to ground (0 V).