Install a Power Supply
Install a Power Supply
Installing a power supply is a hot-swap operation. You do not need to power off the server
before installing the power supply.
1.
Consider your first step.
■
If you are replacing a power supply, remove the faulty or obsolete power supply first, then
“Remove a Power Supply” on page 122
.
■
If you are installing a power supply as part of another component's removal or installation
2.
Align the power supply to the location where it installs into the chassis.
The PDB connector is toward the chassis, and the release tab is on the left.
3.
Slide the power supply into the chassis until the power supply seats and the
release tab clicks.
4.
Attach the power cord.
Servicing Power Supplies
125
Summary of Contents for netra X5-2
Page 1: ...Netra Server X5 2 Service Manual Part No E53601 03 October 2016 ...
Page 2: ......
Page 12: ...12 Netra Server X5 2 Service Manual October 2016 ...
Page 20: ...20 Netra Server X5 2 Service Manual October 2016 ...
Page 59: ...Using the Server Fault Remind Button Detecting and Managing Faults 59 ...
Page 60: ...60 Netra Server X5 2 Service Manual October 2016 ...
Page 128: ...128 Netra Server X5 2 Service Manual October 2016 ...
Page 144: ...144 Netra Server X5 2 Service Manual October 2016 ...
Page 148: ...148 Netra Server X5 2 Service Manual October 2016 ...
Page 154: ...154 Netra Server X5 2 Service Manual October 2016 ...
Page 180: ...180 Netra Server X5 2 Service Manual October 2016 ...
Page 210: ...210 Netra Server X5 2 Service Manual October 2016 ...
Page 226: ...226 Netra Server X5 2 Service Manual October 2016 ...
Page 266: ...266 Netra Server X5 2 Service Manual October 2016 ...
Page 274: ...274 Netra Server X5 2 Service Manual October 2016 ...