96
Sun Datacenter InfiniBand Switch 648 Installation Guide • May 2010
■
“Installing the InfiniBand Software Stack” on page 23
▼
Power On the Fabric Cards for Installation
1. Identify the prerequisite and subsequent tasks you must perform in
conjunction with this procedure, to install the switch.
See the table in
“Installation Sequence” on page 20
.
2. On the CMC, type:
where
slot
is the slot number of the installed fabric cards (
0
–
8
).
When a fabric card is activated, the OK LED is illuminated, the fans spin up, and
the fabric card goes to full power.
3. Repeat
for each installed fabric card.
4. Verify the fabric card status LEDs indicate a normal start up to full power.
The OK LED should be lit and the Attention LED should be unlit. See
Fabric Card Status LEDs” on page 96
Related Information
■
Switch Command Reference
,
activate
command
■
File for Installation” on page 93
■
“Power On the Line Cards for Installation” on page 103
▼
Check the Fabric Card Status LEDs
1. Identify the prerequisite and subsequent tasks you must perform in
conjunction with this procedure, to install the switch.
See the table in
“Installation Sequence” on page 20
.
2. Visually inspect the fabric card status LEDs.
#
activate fc
slot