Follow the instructions of “Concrete Wall Mounted” installation. Anchor bolts shall be installed per-
pendicular to the surface.  

INSTALLATION: WALL THIMBLE MOUNTED 

Required Materials: 

Orbinox Wall Thimble Mounted RB Weir Gates are installed by means of Hex Bolts. In order to avoid 
leakage between the wall thimble and the frame, construction sealant shall be used. (Sikabond Con-
struction  Sealant  or  equivalent,  200ml  per  meter  of  opening  perimeter).  For  detailed  information 
about the size and quantity of the required bolts, or any other specific installation notes or materials, 
please refer to the notes on the „General Arrangement Drawing‟. Note that as standard, bolts and 
construction sealant are not supplied with the slide gate. 

Installation: 

The concrete construction shall be flat, level and plumb, and shall be in accordance to ACI 
117-06 standard. 

If necessary, use non-shrink grout in order to meet the specified standard. 

Apply  construction  sealant  all  around  the  perimeter  of  the  frame.  Sikabond  (200  ml/m)  or 
equivalent construction sealant shall be used. 

Partially tighten the four corner bolts, and check that the weir gate is perfectly lined up with the 
wall thimble opening. 

Install the rest of the bolts, and evenly tighten all of them.  

Summary of Contents for RB Weir Gate

Page 1: ...Installation Operation and Maintenance Manual RB Weir Gate...

Page 2: ...LATION OPERATION AND MAINTENANCE MANUAL MODEL RB WEIR GATES INDEX Introduction Handling and Storage Installation Weir Gate installation Concrete Wall Mounted Concrete Round Manhole Wall Mounted Wall T...

Page 3: ...y the customer prior to the production of the weir gate Orbinox as sumes no responsibility or liability if the slide gate is not installed operated and maintained in strict accordance to the procedure...

Page 4: ...truction sealant shall be used Sikabond Construction Sealant or equivalent 200ml per meter of opening perimeter The following table gives a general description of the required anchor bolt types for th...

Page 5: ...ncrete construction shall be flat level and plumb and shall be in accordance to ACI 117 06 standard If necessary use non shrink grout in order to meet the specified standard Concrete wall surface shal...

Page 6: ...ant application Sikabond or equivalent In order to avoid leakage between the frame and the wall construction sealant shall be applied on the frame Remove the weir gate from the wall first remove the n...

Page 7: ...ll and install the rest of the anchor bolts see Figure 5 CAUTION If the weir gate is not completely in contact with the wall do not over tighten the an chor bolts Over tightening may bend or distort t...

Page 8: ...ll be used Sikabond Con struction Sealant or equivalent 200ml per meter of opening perimeter For detailed information about the size and quantity of the required bolts or any other specific installati...

Page 9: ...2 Insert all stem guides from the top of the stem extension when applicable Align stem extension and especially make sure that it is aligned with the vertical axis of the opening see Figure 7 The maxi...

Page 10: ...A ORBINOX SPAIN ORBINOX UK ORBINOX FRANCE ORBINOX GERMANY ORBINOX INDIA ORBINOX CHINA WWW ORBINOX COM OBXC 05 2010 10 05 2010 Edition Revision INSTALLATION OPERATION AND MAINTENANCE MANUAL MODEL RB WE...

Page 11: ...tion before cycling the weir gate Manu ally open the gate approximately 5 before the initial electric motor operation Check the motor rotation to assure proper direction of the slide travel according...

Page 12: ...and in the guides Check the seals and make sure they are not damaged Seals shall be replaced if damaged See section Maintenance Seal Replacement for detailed procedures about seal replacement Seals s...

Page 13: ...s item 4 UHMWPE guides item 5 and frame Proceed with caution as major components of the gate are no longer se cured Step 3 Remove frame guides item 4 UHMWPE guides item 5 slide item 7 yoke item 6 and...

Page 14: ...DA ORBINOX USA ORBINOX SPAIN ORBINOX UK ORBINOX FRANCE ORBINOX GERMANY ORBINOX INDIA ORBINOX CHINA WWW ORBINOX COM OBXC 05 2010 14 05 2010 Edition Revision INSTALLATION OPERATION AND MAINTENANCE MANUA...

Page 15: ...MAINTENANCE SEAL REPLACEMENT 49 X49 TO 80 X80 Step 1 Start from the open position Step 2 Unscrew bolts item 1 with caution as the slide is no longer secured Step 3 Unscrew bolts and nuts items 10 and...

Page 16: ...ADA ORBINOX USA ORBINOX SPAIN ORBINOX UK ORBINOX FRANCE ORBINOX GERMANY ORBINOX INDIA ORBINOX CHINA WWW ORBINOX COM OBXC 05 2010 16 05 2010 Edition Revision INSTALLATION OPERATION AND MAINTENANCE MANU...

Page 17: ...install the weir gate clean the wall and apply a new layer of construction sealant Loose anchor bolts Tighten anchor bolts Incorrect anchor bolts Check the General Arrangement Drawing and make sure th...

Reviews: