IG-262-EN versión 02; 26/04/2018
11
General instructions
pfu
for large-sized applications
Handling
6.1.2. Handling of bodies with four DEHA anchors
The information presented is only general, not detailed.
Check in advance with
Ormazabal
to determine the
details for the handling tools and equipment.
Two DEHA-type anchors are set out on each long side of
the body.
1
DEHA-type anchors
Figure 6.6.
Layout of DEHA anchors
The body and cover can be handled together.
Proceed as follows:
1.
Make sure the tools and equipment shown in Figure 6.7
are available, ensuring the larger shackle of the lifting
beam is joined to the top slings. The smaller shackle is
attached to the bottom slings or chains. Hook the top
slings on the crane hook.
1
Top slings
2
Lifting beam
2.1
Larger lifting beam shackle
2.2
Smaller lifting beam shackle
3
Bottom slings or chains*
4
Universal-head hooks (DEHA KA-type**)
* Slings or chains, in accordance with the detailed study of the handling
process.
** The tank and body may require different universal head hooks.
Figure 6.7.
Fastening tools set