IG-262-EN versión 02; 26/04/2018
20
Installation
General instructions
pfu
for large-sized applications
8. Installation
When installing the
pfu
at its location, it is essential to
follow current legislation on installations and electrical
networks, local regulations and the specifications of the
utility company. The instructions included in this document
must be followed during electrical installation.
The site must be visited in advance to check if vehicles can
have access and if there is sufficient space for the unloading
and assembly operations, taking into account the distances
to overhead lines, slopes, etc.
8.1. Receiving the equipment
Upon receipt of the enclosure, carefully check the following:
1.
The general condition of the assembly.
2.
Absence of bangs or breakage, especially at the
connection points to other items or close to the DEHA
couplings.
3.
The state of the paintwork, checking for the absence of
chipping, scratches, etc.
4.
Accessories: If damage or absences are observed,
immediately inform the transport agent and
Ormazabal
.
8.2. Location
The site location should be precisely defined, indicating the
levels of alignment and height of the possible reference
points, such as: roads, kerbs, milestones, fences, pavilions,
pylons, etc.
Incorrect levelling may cause the base of the tank or
the body to break.
8.3. Planning
On the location sketch or drawing, mark out the spaces
available for the crane and the transport truck.
D
Maximum length of the crane elevation arm
Figure 8.1.
Offload operation
Check distance D in the particular order instructions.
The existence of any circumstance or object that could
impede or obstruct the smooth operation of the installation
must be indicated (posts, cables, ditches, walls, pipelines,
etc.), marking their positions on the drawing.
Pay special attention to the position the truck crane
to ensure the support jacks are not too close to the
excavation, which could lead to collapse. The support
jacks must be more than 2.50 m from the excavation.
Check with
Ormazabal
to ensure the characteristics of
the crane for handling the
pfu
(nominal crane capacity
at a distance of 3 m, etc.).