IG-123-EN version 11; 23/07/2021
71
General instructions
cpg
.0: GIS medium-voltage switchgear,
gas insulated, up to 40.5 kV,
in accordance with IEC Standard
Operations sequence
8.
Close the cover and check that all the strikers have been
reset.
Figure 7.82.
Fuse holder closure
9.
Position the fuse and cable compartment access cover
(a) by pushing it downward and ensuring it is locked
on the cubicle, taking into account that the fuse status
indicator (b) is green.
Figure 7.83.
Cable and fuse compartment cover closing
10.
Start up the cubicle following the instructions set out in
these General Instructions document.
Summary of Contents for velatia cpg.0
Page 79: ......