6.1. ekor.gid installation
6.1.1. Wall-mounted
The ekor.gid Smart Distribution Management Unit can be
installed on any of the Substation's free walls, regardless of
the number of cubicles it contains.
Figure 6.1.
Detail of wall-mounted
ekor.gid
The ekor.gid unit includes 4 independent lugs that are
installed either protruding to the left / right or protruding
upwards / downwards. This second option is recommended
in those cases where the available width does not leave any
space.
The following steps must be followed for installing the
ekor.gid on the wall:
1. Depending on the limitations of the Substation, install
the lugs on the ekor.gid unit protruding to the left /
right or protruding upwards / downwards.
2. Drill the holes corresponding to the lugs, using as the
lower reference point a height of 1000 mm from the
Substation floor.
3. Use a punch to mark the points where the holes are to
be drilled.
4. Use an M8 bit to drill the two holes where the top part
of the ekor.gid unit will be attached.
5. Fit M8 wallplugs in each of the holes.
6. Insert M8 screws in each of the wallplugs. Take care not
to tighten the screws fully so that the ekor.gid unit can
be supported on the two screws.
7. Hang the cabinet using proper mechanical means and
finish screwing each one of the screws.
8. Once the ekor.gid unit is installed, drill its lower holes.
9. Fit an M8 wallplug in each of the holes and screw tightly
into each of them.
This way the ekor.gid unit is installed at a height of about