General Instructions

ekor.gid 

Applications 

2.4.  Automation

The Automated Transformer and Switching Substations 

include the equipment and technology necessary for 

carrying out the Remote Control and Automation of the 

network, as well as the remote reading of the meters. 

To accomplish this, the Transformer and/or Switching 

Substation includes the following components: 

Equipment for automation of the network installed in the 

Medium Voltage switchgear of the Transformer and/or 

Switching Substation. 

An ekor.gid unit which includes: 

1.  Communication components 
2.  PLC concentrator
3.  Low Voltage network Monitor(s). 
4.  Ethernet gateway  

In cases in which the Substation is automated, in addition 

to having an ekor.gid unit, the Substation includes at least 

one ekor.uct unit or a cgmcosmos-2lpt Compact Cubicle 

with Integrated Remote Control Equipment, through which 

the automation and remote control of the entire Substation 

is carried out. 

Figure 2.5. 

Detail of 

ekor.gid

 in Substation with remote control

The Automation of the Medium Voltage network is an  

ekor.uct Compact Remote Control Unit or a 

 

cgmcosmos-2lpt

[2]

 Compact Cubicle with Integrated 

Remote Control Unit, which has the following functionalities 

implemented: 

1.  Operation and status of the Medium Voltage switchgear. 
2.  Directional fault indication. This functionality facilitates 

the location of damages inside the Electrical network.  

[2] Refer to 

Ormazabal’

IG-177

 General Instructions document for 

cgmcosmos-2lpt 

Compact Cubicle with Integrated Remote Control 

Unit.

3.  Metering of the Medium Voltage electrical parameters: 

voltage, current, active power and reactive power.  

These measurements are meant to optimise the energy 

flows. 

4.  Enable alarms using different sensors: 

 - Water or level sensor

 - Fire or smoke sensor

 - Presence of personnel at the Substation sensor or 

intruder alarm

 - Transformer temperature sensor

 - etc.

5.  Medium Voltage transformer position trip with 

presence of any alarm (fire, water, etc.). 

6.  Communications protocol IEC 60870-5-104 

implemented in the ekor.ccp unit for communicating 

with the Operation Control Centre through the 

 

ekor.gid. 

7.  Web server included with the ekor.ccp Programmable 

Cubicle Controller for consulting all the functions 

available in the ekor.ccp unit as well as modifying 

settings and updating functionality.

8.  Possibility of programming restore-service automations. 
9.  Power supply equipment: 

There is a direct current power supply that is connected 

to the Substation's Low Voltage Board. This power 

supply equipment adapts the direct voltage level to 

the power supply both for internal components and 

all the equipment available in the ekor.gid unit. It also 

charges the batteries included with the ekor.uct unit, 

which allows feeding these components in the absence 

of voltage.

1

IEC 60870-5-104 Communications 

2

V

DC

3

PLC - Low Voltage Communications 

Figure 2.6. 

Automation of the Medium Voltage network

Summary of Contents for velatia ekor.gid

Page 1: ...LIB ekor gid Smart distribution management unit General Instructions IG 175 EN version 02 17 06 2016...

Page 2: ...trical installations This personnel must be fully familiar with the instructions and warnings contained in this manual and in other recommendations of a more general nature which are applicable to the...

Page 3: ...4 4 Low Voltage Monitor s 17 3 4 5 Power Supply Equipment depending on the model 17 3 4 6 Ethernet 18 3 4 7 Connection and Protection Components 19 3 5 ekor gid unit interconnections 19 3 5 1 Telemana...

Page 4: ...ults in fewer errors on site 2 Scalability of the investment The items required for Telemanagement can be installed at an initial phase Subsequently it is possible to add the rest of components requir...

Page 5: ...sses the electrical characteristics of Medium Voltage consumption alarms from the Transformer Substation and faults 4 Automation of the Medium Voltage network 5 Communications This acts as a communica...

Page 6: ...future This is especially the case using the Ethernet communication ports that are available in the communication components of the ekor gid unit 2 2 Monitoring of the Low Voltage network 2 2 1 Basic...

Page 7: ...tivity Possibility of fuse temperature detection Figure 2 3 Fuse detail in Low Voltage board The Advanced Monitoring of the Low Voltage network is implemented using sensors in the Low Voltage fuses of...

Page 8: ...ci unit whose primary purpose is the Monitoring of the Medium Voltage network 1 IEC 60870 5 104 Communications 2 VDC 3 PLC Low Voltage Communications Figure 2 4 ekor gid communication with the Medium...

Page 9: ...he location of damages inside the Electrical network 2 Refer to Ormazabal s IG 177 General Instructions document for cgmcosmos 2lpt Compact Cubicle with Integrated Remote Control Unit 3 Metering of th...

Page 10: ...ation with the Customer Management Centre or the dispatching Centre 1 GPRS 2 PLC Medium Voltage 3 Optical Fibre 4 Radio Isolated communication of the Low Voltage network is possible thanks to the oper...

Page 11: ...nit are shown below 1 Communications Compartment 2 Low Voltage connections compartment 3 Interior enclosure interlock system Low Voltage Access 4 Connection protection and power supply components 5 Co...

Page 12: ...the following layout of elements of the ekor gid Smart Distribution Management Unit 1 Auxiliary terminals 2 Low Voltage Monitor 3 Concentrator 4 ED Module 5 ED Terminals 6 GPRS Modem 7 GPRS Antenna 8...

Page 13: ...e different components Since this is a cabinet with a metallic structure the fire load is minimal 3 1 2 Cubicle mounted The exterior enclosure of the ekor gid s unit is metal using thesamefasteningand...

Page 14: ...ing Substation In this case the Substation includes an ekor uct Remote Control Compact Unit or a cgmcosmos 2lpt Compact Cubicle with Integrated Remote Control Equipment that allows carrying out the fu...

Page 15: ...mm thick sheet 4 Very light weight with a density of 1 2 3 6 kg m2 Half of that of glass 5 Temperature performance limit 80 C without deformation Thispolycarbonateenclosureguaranteescompleteisolation...

Page 16: ...enced to the Low Voltage neutral potential Since the enclosure of the ekor gid s unit is at protective earth potential all the components are integrated on polycarbonate to prevent insulation problems...

Page 17: ...unication components and they send the information from these to the Customer Management Centre 3 4 5 Power Supply Equipment depending on the model The power supply unit is a component connected to th...

Page 18: ...Receiver for Advanced Monitoring of the Low Voltage network 2 MODBUS master 3 10 kV insulation Advanced monitoring of the Low Voltage network 1 Radio Receivers The radio receivers implement the follo...

Page 19: ...e outputs 3P N and 6 current outputs Ia1 Ia2 Ib1 Ib2 Ic1 Ic2 for each Low Voltage board to be monitored The voltage signals are wired to miniature circuit breakers and in the case of current signals t...

Page 20: ...and a hub for the Ethernet connector This component which is housed in the Communications compartment of the ekor gid unit separates and isolates the communications of the power supply and distribute...

Page 21: ...hese Low Voltage sensors are the following 1 The installation of the sensors can be carried out on the existing Low Voltage network they can be installed on the standard fuses 2 The sensors do not req...

Page 22: ...Interior Wall Mounted Distribution Management Unit does not include a power supply unit since it is oriented towards Automated Substations where the power is provided by the ekor uct unit or the cgmc...

Page 23: ...of Low Voltage is carried out 4 3 Interior cubicle mounted ekor gid s The ekor gid s interior cubicle mounted Smart Distribution Management Unit has the following main functions 1 Telemanagement 2 Mo...

Page 24: ...Distribution Management Unit uses the safe power of the charger with batteries benefiting from its layout close to the cubicle mounted automation Additionally this Basic ekor gid unit can carry out th...

Page 25: ...nsions Communications Compartment ekor gid i S Basic mm 337 497 147 ekor gid i L Standard mm 487 497 147 ekor gid s mm 300 300 250 Weight kg 40 Weight kg 30 IP Rating according to UNE 20324 IP3X ekor...

Page 26: ...ation install the lugs on the ekor gid unit protruding to the left right or protruding upwards downwards 2 Drill the holes corresponding to the lugs using as the lower reference point a height of 1000...

Page 27: ...upports have a pair of screws for height adjustment 2 Bolt the supports to the side lugs of the cubicle 3 Remove the cover from the cubicle s control 4 Place the cabinet on the cubicle using the cubic...

Page 28: ...dium Voltage network relays which come out of a packing gland in the Communications Compartment of the ekor gid unit and go to the Monitoring cubicle This circuit is protected by a miniature circuit b...

Page 29: ...ithout any connections is recommended 2 6 current outputs Ia1 Ia2 Ib1 Ib2 Ic1 Ic2 of each Low Voltage board to be monitored and therefore for each Medium Low Voltage transformer available in the Subst...

Page 30: ...wer comes from the ekor uct or cgmcosmos 2lpt cubicle mounted model A With power supply equipment and batteries Low Voltage Monitors 1 Low Voltage Monitoring of the Low Voltage network a single Medium...

Page 31: ......

Page 32: ...Subject to change without prior notice For further information contact Ormazabal Ormazabal Protection Automation IGORRE Spain www ormazabal com...

Reviews: