8
Installation
NOTE: Provide the contractor with a printed copy of the “Building Checklist” on page 10 and review requirements with
them.
Prior to Installation
Locate the Fireplace
Keep the following factors in mind when selecting a location for the fireplace:
Fireplace clearance requirements (review “General Clearances” section on page 15).
Heat release and air intake requirements (review “Heat Release” section on page 16, and “Air Intake Opening” section on
Adequate space for servicing.
Access panel recommendations (review “Access Panel” section on page 22).
Minimum vertical vent rise, allowed horizontal lengths, and number and orientation of elbows (review “Vent Configurations”
section on page 29).
Framing and finishing requirements (review “Framing” section on page 11 and “Finishing” section on page 26).
Front wall installation and finishes to be completed after fireplace and vent installation (review “Step-by-Step Chase
Construction” section on page 25).
Floor or Platform requirements (review “Chase Floor/Platform” section on page 11).
Fireplace Installation
Use the following guidelines to ensure a smooth installation. The installation sequence is divided into three phases: Planning,
Installation, and Startup.
First Trip to Site: Planning
Consult with the contractor and go over all requirements:
Chase framing requirements.
5
/
8
” Type X Drywall (or equivalent) requirements.
Heat release requirements.
Air Intake requirements
Access panel size and location.
Gas and electrical specs and location.
Vent configuration.
Finishing details.
NOTE: Provide the contractor with a printed copy of the “Building Checklist” on page 10 and review requirements with
them.
Second Trip to Site: Installation
Confirm the following items are properly located and built to specification:
Framing (with
5
/
8
” Type X Drywall as applicable)
Platform
Gas and electrical
Access panel (if applicable)
Heat release
Air intake
Clear a path free of any possible obstruction to carry in the fireplace.
Uncrate the fireplace and set in place.
Make sure all zero-clearance metal stand-offs on the outside of the fireplace are fully extended.
Secure the fireplace to the framing by attaching the nailing flanges to the framing. See “Securing the Fireplace” section on
Remove all zip ties.
Optional: Remove gas and electrical components from metal shipping plate if desired.
Move the components to the access panel location. Be mindful of the routing for future service needs.
Install the vent components. See “Vent Installation” section on page 9.
Review the front wall requirements (see “Step-by-Step Chase Construction” section on page 25) and finishing details with
the contractor.
Protect the fireplace and components from damage.