background image

Energize/Startup 

Procedures

Pre-startup Procedures:

1.

Double-check all wiring connections.

2.

Inspect the enclosure to ensure no 
debris or tools have been left inside.

3.  Disconnect all AC loads at the backup 

(or critical) load panel.

4.

Disconnect the AC input feed to 
the GSLC at the source.

De-energize/Shutdown 

Procedures

To de-energize or shut down the OutBack devices:

1.

Turn off (open) the AC circuit breakers. 

2.

Turn off (open) the DC circuit breakers for the battery.  
Wait 5 minutes for the devices to internally discharge themselves. 

3.

Turn off (open) the PV circuit breakers.   

4.

Turn off (open) the GFDI circuit breaker.

5.

Verify 0 Vdc on the first DC bus of the inverter by placing the voltmeter 
leads on         and         .

6.

Verify 0 Vdc on the second DC bus by placing the voltmeter leads on         
and        .

7.

Verify 0 Vdc on one PV circuit by placing the voltmeter leads on          
and        .

8.

Verify 0 Vdc on the other PV circuit by placing the voltmeter leads on         
and        .

9.

Verify 0 Vac on the AC output circuit breakers by placing the voltmeter 
leads on 

and        .  Repeat this step for 

and        . 

900-0162-01-00 Rev A.vsd\Page-3\2014-01-24

©2014 OutBack Power Technologies.  All Rights Reserved.

1

2

3

4

3a

3c

RADIAN Series

In   23.2 V     0.0 A
Out  27.6 V     0.0 A

0.000 kW    0.0 kWH

AUX:  OFF     Sleeping

In   23.2 V     0.0 A
Out  27.6 V     0.0 A

0.000 kW    0.0 kWH

AUX:  OFF     Sleeping

3a

3b

3c

1

2

3

4

WARNING:  Lethal Voltage

Review the system configuration to identify all 
possible sources of energy.  Ensure ALL 
sources of power are disconnected before 
performing any installation or maintenance on 
this equipment.  Confirm that the terminals are 
de-energized using a validated voltmeter 
(rated for a minimum 1000 Vac and 1000 Vdc) 
to verify the de-energized condition.

WARNING:  Lethal Voltage

The numbered steps will remove power from 
the inverter and charge controllers.  However, 
sources of energy may still be present inside 
the GSLC and other locations.  To ensure 
absolute safety, disconnect ALL power 
connections at the source.    

1

1b

1c 1d

1b

1c

1b

1d

2c

2d

Test points 

2c 

and 

2d 

refer to the 

right terminal of each circuit breaker.

2c

1b

2d

1b

WARNING:  Burn Hazard

Internal parts can become hot 
during operation.  Do not 
remove the cover during 
operation or touch any internal 
parts.  Be sure to allow them 
sufficient time to cool down 
before attempting to perform any 
maintenance.  

Functional 

Test Points

Battery Voltage Test Points

AC OUT Voltage Test Points 

(Terminal bus bar = TBB)

PV Voltage Test Points

1a

1b

1c

1d

3a

3b

3c

3b

3c

2a

2b

2c

2d

1b

CAUTION: Fire Hazard

Before energizing, confirm that all hardware 
is installed as shown on the Installation 
page.  Stacking battery terminal hardware in 
any other order can overheat the terminals.

Functional 

Test Points

Battery Voltage Test Points

GRID IN Voltage Test Points 

(Terminal bus bar = TBB)

AC OUT Voltage Test Points 

(Terminal bus bar = TBB)

PV Voltage Test Points

4a

3c

4b

GEN IN Voltage Test Points 

(Terminal bus bar = TBB)

In   23.2 V     0.0 A
Out  27.6 V     0.0 A

0.000 kW    0.0 kWH

AUX:  OFF     Sleeping

In   23.2 V     0.0 A
Out  27.6 V     0.0 A

0.000 kW    0.0 kWH

AUX:  OFF     Sleeping

1b

1a

1

2

3

4

5

3a

3b

3c

4a

4b

5a

5b

2b

6
6

2a

1a

1b

3a

3b

3c

5a

3c

5b

2c

2a

2b

2d

1b

To energize or start the OutBack devices:

1.

Using a digital voltmeter (DVM), verify 48 Vdc 
on the DC input terminals by placing the DVM leads 
on        and        .

Confirm that the battery voltage is correct for the 
inverter and charge controller models.

Confirm the polarity.

2.

Turn on (close) the GFDI circuit breaker.

3.

Verify that the PV input for each charge controller 
is in the correct range of open-circuit voltage and 
confirm the polarity by:

a) placing the DVM leads on        and        , and   

b) placing the DVM leads on        and        .

4.

Turn on (close) the PV input circuit breakers.   

5.

Turn on (close) the DC circuit breakers from the battery bank to the inverter.   

6.

If the inverter is in the Off state, turn it On.

7.

Verify 120 Vac on the AC Output L1 TBB by placing the DVM leads on        and       .

8.

Verify 120 Vac on the AC Output L2 TBB        and       .

9.

Verify 240 Vac between the AC Output TBBs by placing the DVM leads on        and        .

10. Turn on (close) the AC output circuit breakers.   

11. Start the generator if appropriate.  Verify 120/240 Vac on the terminals of the AC input sources. 

12. Turn on the AC input feed to the GSLC at the source.

11. Verify 120 Vac on the GRID IN L1 TBB by placing the DVM leads on        and       .

12. Verify 120 Vac on the GRID IN L2 TBB        and        .

13. Verify 240 Vac between the GRID IN TBBs by placing the DVM leads on        and       .

14. Verify 120 Vac on the GEN IN L1 TBB by placing the DVM leads on        and       .

15. Verify 120 Vac on the GEN IN L2 TBB        and        .

16. Verify 240 Vac between the GEN IN TBBs by placing the DVM leads on       and       .

17. Turn on (close) the AC input circuit breakers.  

18. Turn on the AC disconnects at the backup (or critical) load panel and test the loads.

1

2

3

4

5

3a

3c

3b

3c

3a

3b

4a

3c

4b

3c

5a

5b

3c

3c

4a

4b

5a

5b

1a

1b

6

CAUTION: Equipment Damage

Incorrect polarity will damage the equipment.

1b

2a

1b

2b

!

!

Reviews: