Operational Procedures
Loading the furnace with fuel
STEP 5 : Allow the kindling to burn down to a coal bed. Turn the blower
switch off and open door slowly. Push the coal bed to the rear 25% of the
firebox with a long handled shovel.
STEP 6 : Load fire wood just in side the door and rank as tightly as pos-
sible. Cut wood no longer than 36 inches. Longer cut wood will tempo-
rarily obstruct air flow and cost efficiency.
Do not fill the firebox above
the indicated maximum load line.
STEP 7 : Shut the furnace door and turn the blower switch to the on po-
sition.
Maximum load line
Always open door slowly!
NOTE: If firebox
becomes over-
filled, turn the
blower switch off
and allow the fire
to die down before
removing any fuel.
Remove fuel to
proper contain-
ment for hot fuel.