Chassis Replacement Instructions
Remove Unit from Rack
WARNING: It is recommended that a mechanical lifter (or at
least two people) be used during rack installation or removal
to prevent injury.
AVERTISSEMENT: Pour éviter toute blessure il est
recommande qu'un monte-charge (ou deux personnes au
moins) soit utilisé lors de l'installation ou de l'enlèvement du
support.
1.
Release the two
captive screws
on the bottom front left
and right sides, and slide the chassis out until it stops.
2.
Release the rail
locks
and slide the chassis out onto the
lifter.
3.
Move the chassis onto a secure
ESD-safe surface
.
4.
Unpack the
new chassis
and place it next to the old
chassis.
Transfer Components
Move Inner Sliding Rails
You need to move the attached inner slide rails to the new
chassis:
1.
Remove and retain the
three screws
holding one of the
rails on the side of the old chassis.
2.
Position the rail on the same side on the
new chassis
,
and secure it with the
retained screws
.
3.
other rail
.
Move the Power Supplies
1.
While pressing the release latch toward the handle, pull
the
power supply handle
to slide out of the old chassis.
2.
Slide the power supply into a bay of the
new chassis
until
it locks (clicks).
3.
remaining
power supply.
Install New Chassis in Rack
Install the Chassis
1.
Fully extend the
middle
rails out of the rack.
2.
Using the mechanical lifter, position the
chassis
in front
of the middle rails.
3.
Connect the expansion rails into the middle rails, and
slide the
unit
all the way to the rear.
4.
Secure the unit using the
two captive screws
at the
bottom of the flanges.
Old Chassis
New Chassis
ESD-safe Surface
Screws
Side View
Press