Praktika T-02(K) turnstile
14
4.2.8.
Route RC, PS cables and, if necessary, cables of FA and
ACS inside the housing. Cable routing shall be performed through holes 1
or 2 made in the bottom plate of turnstile. In the upper part - through a
hole of 32 mm diameter as shown in (Fig. 5). Secure cables with cable
ties.
4.2.9.
Align holes in the lower plate of the turnstile together
with anchors in the floor. Check the vertical installation in 2 planes. If
necessary, use appropriate steel underlayers for proper installation of the
turnstile. Fix the housing of the turnstile with 6 screws M12, tightening
them to the corresponding anchors by using a S10 wrench with internal
hexagon.
4.2.10. Connect the required cables (see Section 5), secure them with
cable ties. Place opened and removed parts of the turnstile back in the
initial position.
4.2.11. Remove the protective film from the housing of the turnstile.
5. Connecting turnstile
Connection of RC, PS and ACS is performed with the use of
motherboard.
In order to do it, remove the housing cover (1, Fig. 6)
with a
key. Fig. 7 shows the location of motherboard in the turnstile.