4.2 INITIAL POWER-UP
This paragraph describes the procedure used to power-on the ACX Power Source for the first
time. The steps below are the recommended order of operation.
1. For new installations, check input connections (including proper input voltage). Do not connect
the load at this time. Also verify that the OUTPUT POWER switch is in the OFF position.
2. Switch the INPUT POWER switch to the ON position. The controller display will light up and begin
to present output data.
3. Set the controller for the desired output voltage, frequency, etc.
(Refer to the UPC Operation Manual for adjustment of output parameters.)
4. Set the OUTPUT POWER switch of the ACX to the ON/AUTO position and press the UPC
OUTPUT ENABLE switch to set it to the ON position.
CAUTION
PRECAUTION
DO NOT CONNECT ANY LOADS TO THE OUTPUT OF THE POWER SOURCE UNTIL THE OUTPUT
VOLTAGE AND FREQUENCY HAVE BEEN VERIFIED AS CORRECT.
APPLICATION OF IMPROPER VOLTAGE OR FREQUENCY CAN DAMAGE LOADS.
NE RACCORDER AUCUNE CHARGE SUR LA SORTIE DE L’EQUIPEMENT SANS AVOIR AU PREALABLE
VERIFIE ET VALIDE LES PARAMETRES DE SORTIE TENSION ET FREQUENCE
L’APPLICATION DE TENSION ET FREQUENCE INCORRECTES PEUT ENDOMMAGER LES CHARGES
CONNECTEES A L’EQUIPEMENT
5. Verify proper voltage, frequency and waveform at the output terminal block. If the output is not
correct, set the output to proper values. Refer to the controller manual for details.
6. When the desired output has been verified, turn the system OFF by first setting the OUTPUT
POWER SWITCH to the OFF position and then opening the INPUT POWER SWITCH. Connect
the load.
7. Re-start the unit beginning at step 2, above. Verify that the system delivers power to the load.
WARNING
ATTENTION
LETHAL VOLTAGES ARE PRESENT AT THE INPUT AND OUTPUT TERMINALS OF THIS EQUIPMENT!
DES TENSIONS A CARACTERE MORTEL SONT PRESENTES SUR LES BORNES D’ENTRÉE ET DE
SORTIE DE CET EQUIPEMENT!