7
Electrical Installation
Revision 1.3
- 21 -
7
Electrical Installation
When performing electrical installation, please be certain to install and secure
everything in a way where it is not subject to damage from moving parts, sharp
edges, exhaust systems, etc.
If electrical parts (for example back lights) and wires are removed they have to be reinstalled and to be
checked if they are working.
7.1
Main Power Connections
1. Install the 2 Ga. battery cable securely from pump/motor box to battery.
2. use the inside between the frames next to other cables
3. Secure the cable every 12 inches.
4. Heat shrink lug connection to cable.
5. Assure all connections are tight and securely fastened.
Recommended Cable Routing for Trucks
Body Stringer
Sub Wood
Truck Frame
Cable Staples
Route Cables to
OUTSIDE
of U-Bolts
For trailer installation refer to trailer
manufacturers recommended routing
Battery Cable
2-Wire On-off Cable
Figure 21 Cable Routing for trucks
Never secure cable in a way where it can make contact with other wiring, brake fuel or airlines
etc or get pinched against other objects.
7.2
Circuit Breaker
1. Mount circuit breaker securely in battery box
2. Connect liftgate 2Ga. cable to open stud on circuit breaker
3. Connect 2Ga. jumper from forward most stud on breaker to positive battery post
4. Optional: Cupper Buss Bar at Battery Post
Connect 2 Ga cable
coming from lift gate
Connect here
to Positive
Battery post
150 AMP
Resetable Breaker
R
ES
ET