provide a dedicated ‘Flow Check’ test, the following calculation may be used to determine the
deviation value from the ‘Forward Flow’ test result:

Equation 1

Deviation Value from Forward Flow Test Result

Note: A low measured flow value may indicate the presence of moisture in the internal capillary.
In this case, it is recommended to blow clean, dry air at 2 bar (29 psi) pressure for 2 hours
through the Palltronic Flow Check II unit.

If test results are consistently outside the 5% limit, please contact your local Pall office or
distributor as either the Palltronic Flow Check II unit or Palltronic integrity test instrument may
require service and/or calibration.

4.

Maintenance

The Palltronic Flow Check II unit requires no maintenance except that the battery should be
changed when required.

4.1

Changing the Battery

Open the black cover of the battery compartment by using a coin or a screwdriver.

Remove the old battery and replace it by a new 1.5 V battery type AA (LR06/AM-3) 

The negative (–) terminal of the battery should be inserted into the unit. 

Close the battery compartment.

After changing the battery the ‘Battery failed’ message can be erased by pressing the ‘Start’
button for more than 5 seconds to switch the unit off.

Used batteries should be discarded in accordance with relevant local and national regulations.

The battery will be replaced as part of a standard service and calibration at a Pall facility.

5.

Troubleshooting

5.1

Preliminary Troubleshooting

If any difficulties are experienced with the value measured through the Palltronic Flow Check II
unit, please try the following:

• If the display cannot be activated by pressing the button on the right side, then replace the

battery

• It is possible to operate the Flow Check II unit without the display switched on or

with no battery installed. In this case the atmospheric pressure should be
measured using an independent method of measurement. The reference value of
flow shown on the label should then be corrected by multiplying by the correction
factor given in Appendix A.

• Check that the Palltronic Flow Check II unit is correctly connected to the integrity test

instrument

• Check if the environmental temperature is out of the recommended range between 18 °C 

and 25 °C.

• Check that the integrity test instrument is correctly supplied with the appropriate air supply

and that the air supply is oil and water free

Deviation (%) = 

Measured flow – Expected flow

Expected flow

x 100

Summary of Contents for Palltronic Flow Check II

Page 1: ...USD 2642 Instructions For Use Palltronic Flow Check II Unit Part numbers FC02 FC02M and FC02H...

Page 2: ...its 4 2 2 Standard Functions 4 3 Using the Palltronic Flow Check II Unit 5 3 1 Features 5 3 3 Display Function 6 3 3 Test Preparation 6 3 4 Performing a Flow Check Test 7 3 5 Understanding the Test Re...

Page 3: ...USD2363 Please contact your local Pall office or distributor if you require a copy of the latest revision of any of these documents 1 1 Personal Safety Appropriate protective clothing should be worn...

Page 4: ...Within the pharmaceutical industry there is a regulatory requirement to integrity test filters both before and after use in a production environment Therefore a fully functional integrity test instrum...

Page 5: ...l attached to the enclosure displays the certified flow rate using air at an atmospheric pressure of 1000 mbar 14 5 psi the associated test pressure and the unit serial number The display is switched...

Page 6: ...to extend the battery life The unit displays the pressure in mbar only The test pressure is normally 2000 mbar 29 psi 200 kPa 2 039 kp cm2 3 3 Test Preparation The integrity test assembly comprising...

Page 7: ...ass fail result at the end of the test should be ignored refer instead to Section 3 5 for the interpretation of the result Select a Flow Check test on the Palltronic integrity test instrument for more...

Page 8: ...failed message can be erased by pressing the Start button for more than 5 seconds to switch the unit off Used batteries should be discarded in accordance with relevant local and national regulations...

Page 9: ...for the ambient pressure Check that the test parameters especially test pressure are set correctly these details are available with the Palltronic Flow Check II unit see Section 3 4 for more informat...

Page 10: ...700 107 0 106 0 105 0 104 0 103 0 102 0 101 0 100 0 99 0 98 0 97 0 96 0 95 0 94 0 93 0 92 0 91 0 90 0 89 0 88 0 87 0 86 0 85 0 84 0 83 0 82 0 81 0 80 0 79 0 78 0 77 0 76 0 75 0 74 0 73 0 72 0 71 0 70...

Page 11: ...ain Sweden Switzerland Taiwan Thailand the United Kingdom the United States and Venezuela Distributors in all major industrial areas of the world The information provided in this literature was review...

Reviews: