2.2
FRAME GROUND CONNECTION
INSTALLATION
35
3.
Move one of the meter probes to the third prong terminal (GND).
Either the same reading or a reading of 0 V should be obtained.
4.
If a reading of 0 V at 1 terminal and a reading of 108 V AC-132 V AC at the other terminal
is not obtained, the outlet is not properly grounded. This condition should be corrected by
a qualified electrician (per article 250 of the National Electrical Code).
5.
If a reading of 0 V at 1 terminal and a reading of 108 V AC-132 V AC at the other terminal
is obtained, then set the meter to the "OHMS/RX1" scale, place 1 probe at the GND
Terminal and the other probe at the terminal which gave a reading of 0 V. A reading of less
than 1
should be obtained. If the reading is not obtained, the outlet is not adequately
grounded. See a qualified electrician.
Ω
Summary of Contents for KX-TVS75
Page 2: ...2...
Page 13: ...VOICE PROCESSING SYSTEM OVERVIEW 13 Section 1 VOICE PROCESSING SYSTEM OVERVIEW...
Page 26: ...1 3 SYSTEM BASICS 26 VOICE PROCESSING SYSTEM OVERVIEW Table 6 CO Lines Port 1 4 1 5 8 2...
Page 30: ...1 4 DIGITAL INTEGRATION 30 VOICE PROCESSING SYSTEM OVERVIEW...
Page 31: ...INSTALLATION 31 Section 2 INSTALLATION...
Page 97: ...CUSTOMIZING THE SYSTEM 97 Section 5 CUSTOMIZING THE SYSTEM...
Page 127: ...FINAL SETUP 127 Section 6 FINAL SETUP...
Page 135: ...SYSTEM MAINTENANCE AND TROUBLESHOOTING 135 Section 7 SYSTEM MAINTENANCE AND TROUBLESHOOTING...
Page 166: ...7 5 SPECIFICATIONS 166 SYSTEM MAINTENANCE AND TROUBLESHOOTING...
Page 167: ...SYSTEM FEATURES 167 Appendix A SYSTEM FEATURES...
Page 188: ...A1 SYSTEM FEATURES 188 SYSTEM FEATURES...
Page 189: ...SYSTEM ADMINISTRATION 189 Appendix B SYSTEM ADMINISTRATION...
Page 247: ...SYSTEM MANAGER S GUIDE 247 Appendix C SYSTEM MANAGER S GUIDE...
Page 261: ...MESSAGE MANAGER S GUIDE 261 Appendix D MESSAGE MANAGER S GUIDE...
Page 302: ...D7 LIST OF MODIFIABLE PROMPTS 302 MESSAGE MANAGER S GUIDE...
Page 312: ...312 Glossary...
Page 313: ...Index 313 INDEX...