INSTRUCTIONS CM227
For instuctions in Local Languages
and Technical Support:
www.panduit.com/resources/install_maintain.asp
E-mail:
cs@panduit.com
Fax:
(708)444-6448
www.panduit.com
Recommended (optional) Panduit parts:
UICMPP24BLY
UICMPP48BLY
CPP24FMWBLY
CPP48FMWBLY
CPP48HDWBLY
CPP72FMWBLY
CPP24WBLY
CPPL24WBLY
CPP48WBLY
CPPL48WBLY
Modular Patch Panels
Page 2 of 2
End View
Foam
Figure 6
4. Mount the four support brackets under the enclosure by placing one on each corner support stanchion. Point them
towards the center making a cross from the corners (See Figure 3). The brackets must be mounted low enough for the
enclosure to clear the floor.
5. Locate the enclosure by tilting the unit at an angle allowing clearance of the opening and place it on the support
brackets. The lip of the box is resting against the stringers with the weight of the box supported by the support brackets.
6. Replace the stringers and tighten the screws. Center the enclosure by sliding the unit up the support stanchions.
Tighten the nuts on the support brackets. Use the leveler bolts to level and snug up the enclosure against the stringers.
Insert the foam in the cable entry ports and slide the cover in place. Replace the tiles after cabling and equipment are
installed. The floor tile serves as an access door to the equipment.
To ensure proper installation, the foam is layered tightly around the cables in the cable entrance and exit ports
with foam sheets provided (See Figure 6).
Sold by:
http://www.TWAcomm.com
Toll Free: (877) 892-2666