SMARTZONE G5 USER MANUAL
57
RNA Setup
To setup RNA mode on two PDUs, the user must (1) configure the PDUs for RNA Mode
(using CLI) and then (2) connect the LAN Network cords and Ethernet cords between
PDUs
To Configure RNA Mode in the CLI
1. Login to the CLI and enter the command ‘dev daisy dna.’
2. The following message will appear:
•
Reboot Required for change to take effort.
•
System Reboot now, Are you sure? (Y/N)
3. Enter Y to confirm reboot.
4. After reboot, the PDU will be setup to RNA Mode.
5. Repeat this process for the second PDU.
To Connect the PDUs for RNA Setup
After the PDUs are configured for RNA:
1. Connect an Ethernet cable from the Landlord LAN Network to the Ethernet port
of the first PDU. This will have limited access/permissions.
2. Connect an Ethernet cable from the Tenant LAN Network to the Ethernet port of
the second PDU. This will have full access to both PDUs.
3. Connect an Ethernet cable from the Rs485-1 port on first PDU to the
RS485-2 port on the second PDU.
4. Connect another Ethernet cable from the Rs485-2 port on the first PDU to the
Rs485-1 port on the second PDU.
5. In RNA mode, the default account username is ‘landlord’ and password is
‘12345678’. This account is configured for proper access and control in RNA
mode.
6. To enable this account, login to the CLI with admin credentials.
7. Enter the command ‘dev daisy dna init’.
8. The following message will appear to confirm the landlord account is enabled:
SUCCESS.
Summary of Contents for smartzone G5
Page 1: ...G5 PDU User Manual...
Page 11: ...SMARTZONE G5 USER MANUAL 10 Login Page Introduction to Web GUI...
Page 14: ...SMARTZONE G5 USER MANUAL 13 Environmental Page Security Page...
Page 35: ...SMARTZONE G5 USER MANUAL 34 Connect the RJ 45 end of the cable to the Serial RS485 1 connector...
Page 45: ...SMARTZONE G5 USER MANUAL 44...
Page 50: ...SMARTZONE G5 USER MANUAL 49 FOR 1 PHASE WITH BREAKERS FOR 3 PHASE WITH 6 BREAKERS...
Page 53: ...SMARTZONE G5 USER MANUAL 52 2 Select Outlet Control Enabled...
Page 55: ...SMARTZONE G5 USER MANUAL 54 5 Your Outlet Power Sequence has been set...
Page 59: ...SMARTZONE G5 USER MANUAL 58 9 RNA is now configured and enabled...