Before you perform any checks and/or repairs yourself on your glider, we ask to read you the fol
-
lowing pages carefully. You inform yourself hereby about prerequisites and conditions of a done in
person bi-annual inspection.
– According to new DHV regulation, the customer (Glider-owner) can conduct the 2-yearly check
of the canopy with the help of the inspection directions and all necessary testing equipment and
documents in person on his own responsibility. In addition the wing does not have to be sent in to
the manufacturer.
– The 2-yearly check may only be conducted by the glider owner personally, if he fulfils the prereq
-
uisites, or an inspection station authorized by the manufacturer. Inquire therefore with the manufac
-
turer on authorized inspection stations.
– The owner of the canopy must be aware of the responsibility, which he takes with a self conduct
-
ed 2-yearly check of the glider. The self performed 2-yearly check is only legally effective, if this is
acknowledged after the check with date, name (in capitals) and signature on or beside the placard.
– Reserve equipment re-packing interval in accordance with DHV: Every 4 months a repacking is
required. Allowed period of operation: 8 years, afterwards up to 12 years with an annual check
– About insurance-legal consequences of yourself performed 2-yearly inspection you should inform
with your insurer in a timely fashion.
– An inspection is valid only if the inspection log is completely filled out. Inform also about possible
revisions of the inspection directions with the manufacturer before the inspection.
– Important: If the necessary efforts for the maintenance inspection cannot be carried out (required
equipment and documents), should the canopy be sent in to the manufacturer.
– Any warranty and guarantee will be voided for paragliders, harnesses and reserve parachutes,
which are checked, controlled, repaired, packed or repacked, test-flown and/or have other mainte
-
nance work done by personnel not authorized by Papillon Paragliders!
– All maintenance work must in be accordance with the maintenance specifications of the operation
manual and the special maintenance directions of the manufacturer and the publications of the IHB
to be conducted.
– With any abnormal appearances during the performance of maintenance is the technical manager
to be informed, who has to decide on how to proceed.
– With the replacement of parts or component modules only original materials or original party may
be used!
COMPLETED CHECK VERY IMPORTANT!