Troubleshooting and Maintenance
5-31
9161-A2-GH30-20
September 1997
Procedure
To force signaling:
1. Follow this menu selection sequence:
Main Menu
→
Test
→
Voice Port Tests
2. Enter the desired slot and port number.
3. Press PgDn to go to page 2.
4. Enter the desired setting for each field.
5. Highlight Start under Command in the row to send a test. Then, press Return
to start the test.
6. View the length of time that the test has been running in the Results column.
7. Highlight Stop under Command to stop the test.
Procedure
To monitor signaling:
1. Follow this menu selection sequence:
Main Menu
→
Test
→
Voice Port Tests
2. Enter the desired slot and port number.
3. Press PgDn to go to page 2.
4. Look at the values displayed under the Monitor Signaling portion of the
screen.
Device Tests
The T1 access unit supports a Lamp test at the device level. Use this test to
determine whether all LEDs are lighting and functioning properly. All LEDs light at
the same time every 1/2 seconds during execution of the Lamp test. When you
stop the Lamp test, the LEDs are restored to their normal condition. If the Test
Timeout configuration option is enabled and a Test Duration is set, the Lamp test
stops when the test duration expires. The Lamp test is not disruptive to data.
Test Timeout
A Test Timeout feature is available to automatically terminate a test (as opposed
to manually terminating a test) after it has been running a specified period of
time.
To use this feature, enable the Test Timeout configuration option under the
System Options branch of the menu tree, and set a duration for the test to run in
the Test Duration (min) configuration option (see
Table 4-8
in Chapter 4).