40
Figure 3.3
–
Human-Machine Interface (HMI)/Controller
4.0
COMMISSIONING
4.1
COMMISSIONING CHECKLIST
1.
Inspect - Make sure all external plumbing connections are made per the P&ID diagram. Make
sure all electrical connections to all external devices are connected properly per the electrical
schematics.
2.
Install micron filters.
3.
Install Fresh Water Flushing Filter.
4.
Install Membranes.
5.
Valve Alignment
6.
Ensure that the installation has been properly performed.
7.
Check the RO Membrane Element as described below.
8.
Check the oil level in the HP pump. Be sure it is at the proper level.
Summary of Contents for AQUA DUO A455C-2800
Page 15: ...15 Figure 2 4 Piping and Instrumentation Diagram 2800 3600 GPD ...
Page 17: ...17 Figure 2 6 Piping and Instrumentation Diagram 4800 6200 GPD ...
Page 32: ...32 Figure 2 26 Hose Tube Connection Instructions Figure 2 27 Tubing Fitting Internals ...
Page 63: ...63 8 DRAWINGS DIAGRAMS ...
Page 64: ...64 1 P ID ...
Page 65: ...65 ...
Page 66: ...66 ...
Page 67: ...67 ...
Page 68: ...68 2 GA Drawing ...
Page 69: ...69 ...
Page 70: ...70 ...
Page 71: ...71 ...
Page 72: ...72 ...
Page 73: ...73 ...
Page 76: ...76 4 Wiring Diagrams ...
Page 77: ...77 ...
Page 78: ...78 ...
Page 79: ...79 ...
Page 80: ...80 ...
Page 81: ...81 ...
Page 82: ...82 ...