179560600 Rev1
Page
19
of
21
Appendix 3
PHL 03/05/08 (
Figure 14
)
a)
Remove the filter bowl from the head and place both parts on a suitable surface where they may not be
damaged
b)
Assemble the adjustable feet to the support legs (1)
c)
Screw the support legs (2) into the available locations on the under side of the head (3 positions)
d)
Adjust the feet (1) ensuring the housing is installed level. The foot plate can also be used to bond the
housing to the earthing system.
Clamp, Butt Weld and DIN 11851 inlet and outlet connections
7
e)
Place the gasket seal (3) onto the inlet elbow (4), observing the direction arrows marked. Ensure the correct
elbow is fitted to each respective nozzle on the filter head (Figure 15). Rotate the nozzles to the desired
position then sucure to the housing head using the provided clamp and screws (6).
f)
Repeat the same process with the outlet elbow (5). When connecting to the process pipework, ensure to
observe the direction of flow is in the same direction as marked on the filter housing.
g)
Locate the closure seal (7) to the o-ring grove on the housing head
h)
Fit the filter cartridges, refering to the filter cartridge IOMI, (see also section 6.1)
i)
Fit the cartridge compression plate (8). For 226 (C-Style) filter cartridges, the compression plate locates and
secures over the cartridge fins.
j)
Replace the housing bowl (9) and secure with the closure screw clamp (10).
Lateral Vent Port (
Figure 16
):
k)
Remove the sanitary bleed valve (11) from its packaging.
l)
Loosen the grub screw (12).
m)
Manually screw the valve to the side port (13) located on the filter housing vent/pressure gauge port and
tighten the grub screw to secure on the port.
Figure 14
Figure 15
Figure 16
7
Flange versions: inlet and outlet elbows are welded to the filter housing head