background image

Installation Instructions for 4041-5300 Electrical Connection Kit 

for Self-Regulating Bundles

Instructions for Power Connection 
Note: 
These steps should be followed if making a power connection.

1

If using heat shrink boots, place heat 

shrink boot onto bundle and feed 

heater wire, tube, and other acces-

sories through openings. Heat boot 

carefully until it shrinks down and all 

ends are completely sealed. (HSB-2 

2-leg boot shown is sold separately. 

RTV-103BLK sealant supplied with 

kit can also be used instead of HSB’s 

to seal bundle ends).

Follow steps 1 through 4 of  

“Instructions for Splice or Tee  

Connections.”

2

3

Once in place, prepare heating  

cable end per “Heating Cable  

Preparation,” steps 1 through 6.

5

Parker Hannifin Corporation

Parflex Division

Ravenna, OH USA

www.parker.com/pfd

4

Once cable preparation is complete, 

twist junction box onto the pipe 

standoff.
Make electric splice connection 

inside box with heating cable and 

cable from power source. Using two 

butt splice connectors, splice heater 

bus wires to power source  
Using ring terminals, crimp terminal 

rings onto braided pigtail and tighten 

to back of box with ground screw. 
Wrap bus wire connections  

with fiberglass tape. Bus wire  

connections must not touch inside 

box, otherwise a short circuit will 

occur.

Butt Splice 

Connectors

(before FC 

tape applied)

Braided 

Ground 

Wire

FC Tape

Fitting used in connection  

can be obtained from your  

local Parker Instrumentation 

Distributor.

Typical Power Connection

HSB or  

RTV-103BLK 

sealant

Summary of Contents for Temptrace SL Series

Page 1: ...ing Grommet 4 Stainless Steel Pipe Straps 2 large 2 small 1 3 Hub Box 1 Box Cover 6 Wire Nuts 2 Butt Splice Connectors 1 SK 612 Seal Patch Kit 3 Sleeve Rubber Heating Cable Boot 3 Ring Terminals 2 Cab...

Page 2: ...st be installed prior to installing the base of the heating cable Bundle End Preparation Used in all connection types NOTE The IEEE standards 515 2004 for heating cables require the use of GFEPDs with...

Page 3: ...heating cable to extend beyond sealing grommet for easier power termination Slide the seal grommet over the heating cable and position the grommet in the standoff Note If heater wire is braided only...

Page 4: ...ck of box with ground screw Note One ground screw may be used for both wires if necessary Wrap bus wire connections with fiberglass tape Bus wire connections must not touch inside box otherwise a shor...

Page 5: ...cable end per Heating Cable Preparation steps 1 through 6 5 Parker Hannifin Corporation Parflex Division Ravenna OH USA www parker com pfd 4 Once cable preparation is complete twist junction box onto...

Page 6: ...ble Lightly cut the outer jacket up the center to the end of the heating cable and peal off the outer jacket 2 Push braid back toward outer jacket to create a pucker 3 At the bulge separate the braid...

Page 7: ...re braid CAUTION When cutting heating cable over jacket take care not to cut into bus wires Cutting bus wires may cause electrical malfunctions NOTE Either a hot air gun or propane torch may be used t...

Page 8: ...Bulletin S T II 8 2018 2014 2018 Parker Hannifin Corporation...

Reviews: