Pre-Operation Inspection and Calibration Verification
© PAT
Rev. D 04/12/02 CSH
190072_d.DOC
41
Fig. 1
:
Setting of Anti Two-Block Retainer in Locking
Position
Fig. 2
:
Retainer in Locking Position
3.
Straighten the cable completely into the slot and release the cable (4).
4.
Turn the flag of the retainer for best visibility for the operator (5).
Removal and Storage of the Anti Two-Block Retainer
Procedure (see Fig. 3 and 4):
1.
Pull the cable out of the switch (1) and bend back parallel to the boom and hold (2).
2.
Move the retainer down (3) and then left (4) to remove it from the Anti Two-Block switch. Release the
cable.
3.
For storage slide the retainer from right side (5) over the Anti Two-Block switch until the clips (A) lock
into the holes (B).
Fig. 3:
Removal of the Anti Two-
Block Retainer
Fig. 4:
Retainer in Storage Position