2.5 Location Setup
Foundation
The appliance must be installed level, on a housekeeping pad, to function properly. Ensure the base is
securely connected to the appliance. Use a bubble level and make sure housekeeping pad is level
before installation of appliance. There are four
3/4” holes in the base which may be used for 5/8”
anchor bolts. Two of these are located inside the cabinet and the other two are outside.
The
housekeeping pad must be at least 4 inches in height.
NOTICE!
The appliance may be installed on a combustible floor; however, the appliance must
NEVER
be installed on carpeting.
NOTICE!
Check the rating plate for indoor or outdoor use.
QTY 2: 3/4” Holes
for
Anchor/Lag Bolts
(REAR)
QTY 2: 3/4” Holes
for
Anchor/Lag Bolts
(FRONT inside
cabinet)