3 Assembly and installation [specialist]
10
997655910x-mub-en
–
V07
2016/05
Optionally available!
7.
Connect the pipe for the expansion tank below
the pressure gauge [7.5] and fix the bracket
for the expansion tank.
8.
Adapt the initial pressure of the expansion
tank to the installation and connect the
expansion tank. Please observe the separate
instructions regarding the expansion tank!
9.
Check all thread connections and tighten
them if necessary.
WARNING
Risk to life and limb due to electric shock!
Prior to commencing electrical work on the controller, pull the mains plug!
Only after completing all installation work as well as the flushing and filling,
the mains plug of the controller can be plugged into a socket.
An unintentional start of the motors is thus avoided.
10.
Connect the pumps and the sensors to the
controller.
The assembly of the solar station is now
completed and the station can be put into
operation.