Page 5 of 7
13.
14.
With the mains plug connected and mains
power on, switch on the generator at the front
panel.
The green ready LED will pulse throughout
its start-up procedure. The fascia panel
will indicate an increase in pressure after
25 minutes. Start-up completion is
indicated by a solidly illuminated green
ready LED. This will take up to 3 hours.
**NOTE**
The generator must be allowed to complete its start up procedure, as per step 14. This time
should be utilised by connecting suitable fittings to the application. However, do not connect
the generator at this time.
15.
16.
After completion of the start-up
procedure, switch the generator power
OFF
at the switch on the front panel.
The Zero Air pressure should be
allowed to dissipate before proceeding.
Connect the 1/8” copper tube to the Zero Nitrogen
and Zero Air compression fittings. The other ends
should be connected to the correct inlets of the
application.